How to arrange the pipeline of trailer concrete pump?

2020.08.19 759  Font size

As a kind of concrete conveying pump which is used very much by the construction party at present, the towing pump is popular among construction parties because of its wide application range and low cost. However, in the process of use, trailer concrete pump also has its limitations. If the pipeline is to be laid, how should the pipeline of trailer concrete pump be arranged? Now we introduce it as follows.

 

Experts point out that there must be a few key points to pay attention to when the pump is laying pipelines, so as to ensure that there is nothing wrong in the construction process. So what are the key points to be grasped by trailer concrete pump during pipeline laying? Specifically, the pipeline arrangement of trailer concrete pump can be implemented from the following aspects.

 

1. When arranging trailer concrete pump pipeline, it shall be ensured that the length is shortened as much as possible, and the pipe bend is reduced to reduce the resistance of transportation, under the premise of smooth pumping and normal transportation.

 

2. It is best to connect a straight pipe more than 2 meters in front of the tapered pipe before using the elbow. It should also ensure that the axis of the straight pipe coincides with the axis of the tapered pipe and that it is fixed and reliable so that the tapered pipe can be quickly installed after disassembly return.

 

3. Each pipeline must be firmly connected, and a firm fixing device must be installed at the bend. A firm point must be set for every 10 meters of horizontal pipelines, and the pipeline clamps must be suspended to facilitate the removal and connection of pipelines. The clamps must be fastened in place to ensure that the joints are tightly sealed and do not leak slurry or water.

 

4. Take over according to the site construction conditions and the requirements of takeover, and arrange the pipelines reasonably to eliminate hidden dangers.